TUJUAN SEMINAR PENGURUSAN TUNTUTAN EOT LOSS EXPENSE KONTRAK PAM 2018 & PAM 2018 NSC


PROBLEM STATEMENT

It is common to notice nowadays that almost all construction projects do not finish in their original contractual finish date. This happen due to so many reasons which may come from the contractor’s own mistake, neutral events, other third party and employer’s act of prevention. When delay was due to Contractor and Nominated Sub-Contractor’s mistake, the Architect will be quick to issue CNC and the Employer will not hesitate to immediately impose LAD. This happen because the contract does not impose strict and tedious procedures for the Employer to deduct LAD.

On the other hand, if delay was due to Employer’s act of prevention, the contract stipulated endless and tedious process and procedures which must be complied with by the Contractor and Nominated Sub-Contractor’s before they can succeed in their claim for EOT and Loss and Expense from the Employer. Unfortunately, not many Contractor and Nominated Sub-Contractor are aware about this endless and tedious procedures which was purposely included in the construction contract. Due to this poor understanding and awareness, a lot of Contractor and Nominated Sub-Contractor have lost their right to a fair EOT and Loss and Expense which they are supposed to be entitled to. There was a dispute with regard to this issue and eventually referred to the Court. The poor Contractor claim for Loss and Expense from the Employer in the amount of RM 12 million. The Court however rejected the whole of the Contractor’s claim. The main reason for that rejection was because the Contractor had failed to comply with the tedious claiming procedures stipulated by the contract.

It is believed that there are many more cases where the Contractor and Nominated Sub-Contractor failed to claim for EOT and Loss and Expense. This has cause them to lose money which they are supposed to be entitled to had they complied with the contract. Loss and Expense is a claim for reimbursement for cost which they have incurred due to Employer’s mistake during the delay period. Losing this claim shall mean they have to pay for other party’s mistake and thus reduce their profit or increased their loss.

To overcome the problem, it is imperative for the Contractor and Nominated Sub-Contractor to wake up and equip themselves with knowledge which can benefit the company, especially the knowledge on how to succeed in claiming for a fair EOT and Loss and Expense. They have to start sending their project team members to Seminar that offers the relevant contractual knowledge.

 

COME AND JOIN OUR SEMINAR

 

SEMINAR OBJECTIVE

The objective of this seminar is to guide contractors and sub-contractors (NSC) on how to manage claim for time and costs in a more strategic, systematic and structured approach based on requirements set under PAM 2018 (MC) & PAM Sub-Contract 2018 (NSC) form of contract. Effective management will enhance the clarity and persuasiveness of their claims and at the same time will ensure compliance with the procedures set by the contract. A well-organized claim document, supported by relevant detailed particulars of the events and costs and comply with the contract procedures will avoid the claim from being disputed and rejected by the Architect and Employer. At the same time, a systematic and structured claim presentation which comply with the procedures will expedite the approval process and payment. This will enhance good and stable project cash-flow.

 

WHAT PARTICIPANT WILL GAIN

In this seminar, participants will be guided on how to prepare a systematic and structured claim which complies with the strict process and procedures set under the contract, for the following type of claims: 

        i.            Additional expenses caused by Variation Works under clause 11.7 of PAM 2018 (MC) & clause 12.3 of PAM Sub-Contract 2018 (NSC).

       ii.            Extension of Time under clause 23 of PAM 2018 (MC) & clause 21 of PAM Sub-Contract 2018 (NSC).

     iii.            Loss and Expense under clause 24 of PAM 2018 (MC) & clause 22 of PAM Sub-Contract 2018 (NSC).

It must be noted that based on the contract provision, strict compliance to all of these process and procedures are “condition precedent” to a successful claim. As such, any failure to strictly comply with any of the conditions (process and procedures) stipulated by the contract, will render the claim to be invalidated and rejected. Any rejection will cause the poor contractor and sub-contractor to suffer in which they will lose money which they have already spent due to other’s fault.

Important to note, that the process and procedures set under PAM Sub-Contract 2018 (NSC) is slightly differ and a little bit more cumbersome as compared to those under PAM 2018 (MC). Claims under PAM Sub-Contract 2018 (NSC) requires the Nominated Sub-Contractor to request contractual cooperation from the Main Contractor. This requires the Sub-Contractor to effectively communicate with Main Contractor within the short time frame stipulated by the contract. Poor communication will lead to poor cooperation and poor cooperation will jeopardize the claim and will eventually create contractual dispute between the parties.

 

HOW THIS SEMINAR WILL BE CONDUCTED

To further clarify the strict process and procedures, in this seminar, we will also discuss and highlight common mistakes and non-compliances which industry players did in the management of the above type of claim as reported and pronounced in the ground judgment of a few local case laws. Based on these pronounced cases, there were mistakes made by contractors and sub-contractors (NSC) and also there were mistakes made by Architects and consultants with regard to the compliance with the process and procedures set under PAM 2018 (MC) & clause 21 of PAM Sub-Contract 2018 (NSC). These mistakes must be avoided.

In order to avoid all of these mistakes, participant will be guided on how to build proper claim templates which aligned with the requirement stipulated by PAM 2018 (MC) & PAM Sub-Contract 2018 (NSC). Few ready-made templates will be discussed and pass as seminar notes.

The seminar will be held in an interactive way. Participant will be encouraged to interact and engage with the speaker at any time during the course of the seminar. This is to ensure that every participant understand the content of the seminar well and able to practice what they have learned for the benefit of their company and their own professional career development.

 

LECTURER

This seminar will be led by Tn Hj Ismail Hj Omar.  He has served in the public and private sectors both locally and abroad. Throughout his career, he has managed several large projects and involved in various construction methodologies for the construction of buildings, highways, treatment plants, railroad tracks and industrial parks, to name a few. As a Project Manager, he has proudly head, managed and accomplished projects worth more than RM 900 million.

In the course of his career as Project Manager, he has managed a few types of construction contracts including PWD 203 series of standard form of contracts, PAM 2006 and FIDIC standard forms. Based on his wide experience and expertise in Project Management he has authored four e-books for Correspondences Templates based on terms and conditions under PWD 203A, 203N, PAM 2018 & PAM Sub-Contract 2018. He also acts as Claim Consultant for contractor who wish to bring their dispute to CIPAA or Arbitration.

 

No comments:

Post a Comment